What should I do if the developer collects the deed tax on my behalf but delays paying it for a long time?

The deed tax should be paid by the purchaser, and it is a service provided by the developer to collect it on behalf of the purchaser. If the developer withholds and fails to pay the tax, which results in the inability to obtain the certificate, the purchaser may request a refund and compensation, and may report the matter to the tax and housing departments or file a lawsuit against the developer.

Learn more >
15 2026-10

When can I get back the quality assurance deposit?

The defect liability period is generally one year, with a maximum of no more than two years. Upon the expiration of the period, the contractor may apply for a refund. The employer shall refund the contractor within fourteen days after verification, and shall bear corresponding responsibilities if the refund is delayed.

Learn more >
15 2026-10

How to claim compensation for the losses caused by the suspension of work?

If the construction is suspended due to the employer's reasons, the contractor may extend the construction period in accordance with Article 803 of the Civil Code and request compensation for the losses caused by the suspension of construction and idle labor. The contractor shall notify the employer in time, handle the formalities of signing the visa, and fix the evidence of the expenses.

Learn more >
15 2026-10

The penalty for project delay is too high. Can it be adjusted?

You can request a reasonable reduction. Article 85 of the Civil Code stipulates that if the agreed penalty for breach of contract is excessively higher than the actual loss, you may request a reduction, but you must provide evidence based on the actual loss to defend against the claim.

Learn more >
15 2026-10

Who will bear the cost increase caused by the design changes?

For the increased project quantity due to the employer's instructions or design changes, the employer shall bear the responsibility in principle. The payment shall be settled in accordance with the agreement or the pricing standard at the time of signing the contract, and the visa formalities shall be handled in a timely manner.

Learn more >
15 2026-10

Can the fixed-price contract still be adjusted?

Where the parties have agreed to settle the project cost at a fixed price, the request for an appraisal of the project cost is usually not supported; however, changes in the design, increases or decreases in the project quantity, and other matters beyond the scope of the agreement may be adjusted in accordance with the agreement.

Learn more >
15 2026-10

Is the project settlement based on the audit conclusion?

Generally, the audit conclusions are not the final basis. If the parties have agreed on the pricing standards or methods, they shall settle the accounts according to the agreement. Unless it is explicitly agreed that the audit shall be the final basis, the audit cannot replace the settlement basis.