[Direct answer]In the Beijing area, if you disagree with the determination of illegal construction, you can apply for administrative reconsideration or file an administrative lawsuit to revoke the determination according to law. According to Article 64 of the Urban and Rural Planning Law of the People's Republic of China and the Administrative Enforcement Law of the People's Republic of China, if a construction project does not obtain a planning permit or is not constructed in accordance with the permit, the competent urban and rural planning department shall order it to be demolished within a specified time limit. If the party disagrees with the determination, it may apply for reconsideration or file a lawsuit within the statutory time limit. Whether the determination is valid depends on whether there is indeed no permit, whether it can be corrected, and whether it is the only housing, etc. It is recommended to first verify the subject and basis of the determination document, and then take targeted remedial measures. For more details, please refer to the following link:Legal services for land expropriation and demolition, and administrative litigation.
I. Problem background and typical scenarios
Demolition of illegal buildings and expropriation often occur concurrently. Typical scenarios include: houses built in the early years with incomplete procedures, which are identified as illegal buildings when expropriated and used to reduce or deny compensation; neighboring rights holders reporting to the administrative authorities for investigation; and the parties themselves adding or expanding buildings that are discovered during inspections. Many parties only realize the urgency of the relief period after receiving the "Order to Demolish within a Time Limit", but they cannot provide planning permits or historical approval materials. The key to such cases is to first clarify the time of the building's construction and the planning management requirements at that time, and then determine whether it is legal. For cases involving disputes over housing ownership, it can be combined with other evidence to prove the legitimacy of the building.Legal services for real estate transactions and construction projects.
II. Key points of dispute
The disputes over the identification of illegal construction focus on three points. Firstly, the identification subject and authority: the order to demolish within a specified time limit must be issued by the statutory urban and rural planning authorities, and the powers of township governments are strictly limited. Secondly, factual identification: whether it is indeed unlicensed and whether corrective measures can be taken to eliminate the impact directly affect whether demolition or a fine and subsequent re-application are required. Thirdly, procedural legality: whether the investigation, notification, hearing, and service are in compliance with regulations. Procedural defects may lead to the revocation of the identification. The disputes also lie in the connection between historically unlicensed buildings and expropriation compensation. Many places have lenient policies for buildings built during specific periods. For cases involving compensation linkage, reference can be made to relevant provisions.Legal services for creditor-debtor disputes and enforcement casesUnderstand the concept of property preservation.
III. Professional analysis by Henglue Law Firm
Based on our practical experience in handling demolition-related cases, the most easily overlooked aspects are the statute of limitations for seeking remedies and the preservation of evidence. Henglue Lawyers usually recommend the following: Calculate the 60-day period for administrative reconsideration and the six-month period for litigation from the day of receiving the determination document, and never wait until receiving the notice of forced demolition to take action; simultaneously collect proof of the construction date, certificates from the village committee or neighborhood committee, and information on the handling of similar buildings during the same period, to demonstrate the historical background of the building; if the administrative authority fails to inform the party of their right to seek remedies, they can claim that the procedure is illegal. In practice, it is easier to obtain a correction rather than a demolition order if the party can prove that they have applied for procedures but were not issued a certificate due to the administrative authority's reasons, or if the building is the only residence of the party. In cases involving conflicts between individuals, relevant evidence can be combined with other materials to strengthen the argument.Criminal defense and legal services for criminal case filing.
IV. Practical suggestions and legal basis
The core provisions include: Article 64 of the Urban and Rural Planning Law of the People's Republic of China (amended on April 23, 2019), which stipulates that if a construction project fails to obtain a construction project planning permit or is built without authorization, the competent department shall order it to stop construction, make corrections within a specified time limit, or demolish it; Article 68 concerning the sealing of construction sites and forced demolition; Article 44 of the Administrative Enforcement Law of the People's Republic of China (implemented on January 1, 2012), which stipulates that the forced demolition of illegal buildings must be announced and the parties be ordered to demolish them within a specified time limit. If the parties fail to appeal, file a lawsuit, or demolish the buildings within the legal time limit, the forced demolition may be implemented; Article 24 of the Regulations on the Acquisition and Compensation of Houses on State-Owned Land (implemented on January 21, 2011), which stipulates that no compensation will be provided for structures identified as illegal; and the provisions of the Administrative Procedure Law of the People's Republic of China (amended in 2017) concerning the time limit for filing a lawsuit. Suggestions: If you disagree with the determination, promptly file for reconsideration or litigation and apply for a stay of execution. You can seek assistance from legal professionals or other relevant institutions to safeguard your rights and interests.Special services and legal services for other cases.
5. Henglu Law Firm's Reminder
Do not wait passively when it comes to identifying illegal construction. The time limit for reconsideration is only 60 days, and the time limit for litigation is six months. If the time limit is exceeded, you will lose the opportunity for relief, and the administrative authority may forcibly demolish the building according to law. It is recommended that you immediately verify whether the authority that made the determination has the necessary qualifications, whether there is evidence to support the facts of the determination, and whether the notification and hearing procedures have been carried out after receiving the document. For buildings that were constructed years ago with incomplete procedures but have not been dealt with for a long time, collect historical usage and neighborhood certificates to strive for leniency. Do not demolish the building or resist law enforcement on your own before the dispute is resolved, so as to avoid exacerbating the losses. If you need assistance, consult a lawyer as soon as possible to assess the legality of the determination and the path of relief. For more details, please refer to the following link:Legal services for land expropriation and demolition, and administrative litigation.
VI. Frequently Asked Questions
Q1: If I receive a determination of illegal construction, can I definitely have it revoked through administrative reconsideration or litigation?
Not necessarily. Whether the court or the review authority revokes the decision depends on whether there are flaws in the facts and procedures. If it can be proven that the building went through the application procedures but was not issued a certificate due to the administrative authority's reasons, or that the review authority lacks the necessary qualifications and failed to perform the notification and hearing procedures in accordance with the law, the probability of revocation is higher. If it can be proven that the situation can be rectified rather than requiring demolition, it may be changed to a fine and a chance to reapply. However, if it is indeed unlicensed and cannot be rectified, and does not meet the lenient policies, the review authority is likely to maintain the original decision. The outcome is influenced by evidence and local policies. It is recommended to collect evidence as soon as possible and seek remedies within the time limit.
Q2: If I disagree with the determination of illegal construction, what evidence do I need to prepare?
The key evidence includes: the "Decision on Ordering Demolition within a Time Limit" or other official documents that determine the relief period and the authority responsible for the demolition; proof of the construction date, such as old land deeds, early photos, and water and electricity connection records; written certificates from village committees, neighborhood committees, or neighbors regarding the construction time; receipts or correspondence from relevant departments regarding applications for permits; the handling of similar buildings during the same period, which demonstrates inconsistent enforcement standards; and proof that the house is the only residence of the owner. The evidence should be organized around the three key points: "formation time—whether it can be corrected—whether the procedure is legal". The more complete the evidence is, the more likely it will lead to the revocation of the demolition order or a favorable judgment in the case.
Q3: How much does it cost to hire a lawyer to handle the determination of illegal construction?
Such cases are usually charged on a per-case basis, with fees related to the building size, whether there are compensation disputes, and the workload. The specific fees are subject to the contractual agreement, and there is no uniform standard. If the determination of illegal construction is related to expropriation compensation and involves significant property interests, some law firms charge fees based on a percentage of the total value of the case. Compared with the value of the house that may not be compensated directly, the investment in the early stages of review and litigation is often worth it. It is recommended to clarify the charging method, stages, and scope with the law firm before entrusting them with the case. For cases involving only review statements and legal opinions, you can choose lightweight services to avoid spending money blindly.
Q4: How long does it typically take from the review of an illegal construction to its eventual demolition?
The review authority shall make a decision within 60 days from the date of acceptance, and the period may be extended by a maximum of 30 days if the case is complex. For cases directly filed as lawsuits, the first-instance ordinary procedure of administrative litigation lasts six months, and the summary procedure lasts 45 days. Only when the administrative authority fails to review the case, file a lawsuit, or demolish the building within the statutory time limit can it forcibly demolish the building according to law, and it must first issue a public notice. Therefore, from the identification to the possible forced demolition, it takes at least the period of review or litigation plus the period of execution notice, often lasting several months. It is recommended to take action immediately upon receipt of the document, and not to wait until the notice of forced demolition is approaching to seek remedies, so as not to lose the protection of the legal process.
Q5: If I disagree with the determination of the illegal construction, what should I do first?
It is recommended to follow four steps: Firstly, make a copy and keep it on the day you receive the document, record the issuing authority, document number, and the date of delivery, and immediately calculate the 60-day period for administrative reconsideration and the six-month period for litigation; Secondly, collect materials such as the construction year, application procedures, and neighborhood certificates to determine whether the identified facts are true and whether the procedures are in accordance with the law; Thirdly, within the time limit, choose to apply for administrative reconsideration or initiate administrative litigation, and may request a suspension of execution to avoid forced demolition; Fourthly, if the identified facts involve related expropriation and compensation, simultaneously claim compensation rights, and when necessary, consult a lawyer to develop a parallel plan for reconsideration and litigation, and strive to obtain corrections or revocations in accordance with the law.
This article is written based on the common judicial interpretation in the Beijing area. If the case occurs in other regions, it is recommended to consult local lawyers to verify the regional differences.
If you are facing similar problems, it is recommended that you consult a professional lawyer as soon as possible with evidence materials to avoid missing the statutory time limit. →Legal services for land expropriation and demolition·Beijing Henglu Law Firm
Disclaimer: This article is compiled based on the current effective laws and regulations and public adjudication rules, and is for general reference only. It does not constitute a formal legal opinion on specific cases. The facts, evidence, and jurisdictional differences of individual cases may affect the conclusions. If you encounter disputes, please consult a practicing lawyer in time.